Tuesday, September 13, 2011

Iteration 1 Plan and Status Documentation

Here we have tried to come up with documentation to indicate the progress or work for this iteration


DELIVERY 1 - ITERATION 2


End user feedback and change requests

  1. Remove edit/ select from grid view
  2. Customer search option
  3. Correspondence site among customer sites
  4. Create site together with customer
  5. No View for customer list
  6. Add site link to main page
  7. Prompt user for confirmation before creating customer
  8. Modify menu on main page
Additional team modifications
  1. Customer codes should be alphanumeric and sorted
  2. Include detail view
DELIVERY 1 , ITERATION 2 PLAN  

Planned Duration
Planned Start Date
Planned End Date
3 days
30th Aug 2011
2nd Sept 2011
Actual Duration
Actual Start Date
Actual End Date
5 days
30th Aug 2011
6th Sept 2011

GROUPED TASKS AND ASSIGNMENTS

Sub-Team A:      Durand and Aylin
Sub-Team B:      Edward and Sara


MODIFICATION TASK
USER INTEFACE
ASSIGNED TO
1.1
1.2
1.3
·         Modify menu structure
·         Include Add site link
·         Customer search link

Main Page
Sub-Team B
2.1

2.2

2.3
·         Create site together with customer
·         Prompt user to confirm creation of customer
·         Sorting - customer codes and site codes
Create Customer Page
Sub-Team B
3.1

3.2
·         Remove Edit /Select from Grid view
·         Include Details View

Customer Details Page
Sub-Team A
4.1
·         Customer Search on code and name

Search Customer Page
Sub-Team A
5.1

5.2
·         Create site for existing customer
·         Add Correspondence site among customer sites

Add Site Page
Sub-Team A

DELIVERY 1, ITERATION 2 STATUS


MODIFICATION TASK
Status
Date Completed
1.1
1.2
1.3
·         Modify menu structure
·         Include Add site link
·         Customer search link

Done
Done
Done
31/08/2011
30/08/2011
30/08/2011
2.1

2.2

2.3
·         Create site together with customer
·         Prompt user to confirm creation of customer
·         Sorting - customer codes and site codes
Done

Done

Done
30/08/2011

30/08/2011

30/08/2011
3.1

3.2
·         Remove Edit /Select from Grid view
·         Include Details View

Done

Done
30/08/2011

31/08/2011
4.1
·         Customer Search on code and name

Done
02/09/2011
5.1


5.2
·         Create site for existing customer

·         Add Correspondence site among customer sites

Modified – included in Customer details

Done
02/09/2011


31/08/2011

Final Integration and Mop-up:   06 Sept 2011


Iteration 2 Timeline and cycle breakdown