Iteration 2 Plan, Reflective Workshop, Methodology shaping session

After yesterday's meeting with end-user and gathering the necessary requirements to progress into the 2nd iteration, we were back to have our iteration plan.

Reflective Workshop
We held this session to identify our working habits, see the things we are doing right that we should keep, those that we should try and the the problems being encountered. Below is a summary of what was collected from the session

Keep These
Try These
·        Effective communication habits
·        Personal Safety
·        Daily stand-ups
·        Frequent feedback on part A – Weekly
·        Pair programming
·        Adjust time to cover for work load
·        Assign development tasks
·        Have agreed screen designs ready for all before development
·        More documentation
·        Provide template document for teams to fill during tasks

·        Introduce voice recording during feedback with permission
Problems

·        Not enough feedback time on Research section





Method Shaping (Methodology Shaping in Crystal Clear)


Alistair Cockburn,  Crystal Clear 2005



Here is a refined process cycle we ended up with after discussing the terms such as what a delivery, iteration, increment , integration should be in terms of our project. 

Refined Process cycle - Courtesy Alistar Cockburn
From the above, we consider our whole project having one delivery with 3 iterations. We replace the terms integration with the term increment based on our understanding and considering the process diagram explanations in Alistair's book (pp 116). We have therefore had to update all references to these terms in our documentation.

Iteration 2 Plan

After using the blitz planning technique to identify all the needed pages and functionality, we divided the tasks once again according to sub groups and scheduled development to start the next day. These outputs were however ready by the close of day

 Database Tables - Task Done by Durand

  •  Project Table 
  •  Stage Table 


 UI screen drafts - Done by Aylin

  •  Add Site Page 
  •  Create Project Page 
  •  Project Details Page 
  •  Site Details Page  


Tuesday, September 13, 2011

Iteration 2 Requirements Gather

After meeting with User on iteration 1, we were poised to start the 2nd Iteration. Below is the requirements specification we gathered from end-user.


• Create Project Page, Specify start and end dates of project
• Allow for update on end date only
• Create project stages. Project stages are of four pre-defined types, Start-up, Initiation, Testing and Documentation. Projects have ids and project stages have ids.
• On Stage creation, specify stage start date and end dates

Additional team suggestions
1. Update Class and Entity relationship diagrams
2. Update database table


Iteration 1 User View and Feedback

Date: 13-09-2011
Meeting time: 1:00 pm - 2:00 pm
Venue: TG 11 Office
Attendance: ALL  + Steve

Meeting was held to show the status of work regarding iteration 1 as well as receive feedback on PART A. We were able to show documents for History of OOA/D , UML, Agile MDA/ MDE, Comparison of Agile Methods. Feedback received identified several errors that have to be amended in the research though he was pleased we presented something.

Feedback of the system developed so far showed so satisfaction from end-user. Minor changes requested and  new requirements given from Iteration 2 on Project Management.

There seems to be a confusion of terms regarding iteration and increment, delivery etc. We plan to hold a method shaping in order to clarify these issues amongst the team.

Details will be looked at in the next group meeting, here is a brief overview of some change requests noted


  • Customer Details Page: there will be a options only as button or link for Add Site, Update Customer Details, and Update Existing Site Details.
  • Site Management on the main page will go under Customer Management and
  • Our third Heading will be View and Reporting

And 2nd iteration is Project Management 
  • Creating Project (going to include Customer details while adding Project)
  • Update Project / Updating Estimated Actual end date
  • All three codes (Customer, Project and Site) will some how combined





Next meeting: 14-09-2011 11:00 am

Tuesday, September 6, 2011

Iteration 1 , 2nd Increment - Day 4

Date: 6th Sept 2011
Meeting time: 11:00am - 12:15pm
Venue: Sheppard Library SG 223
Attendance: ALL

Today's meeting was work on the final integration for the 2nd iteration. 90% of the integration had already been completed. The team sat to to identify errors whiles one person was using it. The application was projected for all to see. Through team work we were able to spot issues that needed resolving and did them right there and then. At the end of the day everyone was satisfied because there was input from everyone. The completion ritual for a one week iteration cycle according to crystal was to review our working habits and providing emotional closure. That was achieved today will everyone being satisfied with the output and progress of work so far. We plan to have a post-iteration workshop after delivery to the user who was give us further feedback to work on. The next meeting with the user is scheduled from friday 09-Sept-2011.

Friday, September 2, 2011

Iteration 1 , 2nd Increment - Day 3

Date: 02-Sept- 2011
Meeting time: 11:00am - 1:30pm
Attendance: ALL

Stand up meeting results

Sub-Team A: Having completed the tasks from sub-team B this days activities hinged on the work from sub-team A. They indicated that they have been able to largely complete the search functionalities which was proving difficult. The problems encountered had to do with a control not updating appropriately.

Integration Session
It was agreed that today will be used for final integration of all that has been developed so far. We were able to integrate some pages which was easy using Visual studio. The integration session revealed that though Sub-Team A had done the search function the tasks requested of them was not exactly what they presented - mainly with User interfaces as well as follow of events. The sub team had to therefore go back and redesign their interfaces to match the Task list. Arguments ensued on how the user interfaces and flow of events must be.
We had to go back to the Story boards we created to verify what we agreed on in terms on user interfaces.

With that settled, Durand was tasked to do the modifications. Edward opted to stay and help him out. The other team members were left to keep working on PART A and the Literature Review of the entire Project.

Close of Day: Before close of day, the two were able to do all modifications and integrate the changes into the final system. 

Wednesday, August 31, 2011

Iteration 1 , 2nd Increment - Day 2

Date: 31-Aug-2011
Meeting time: 11:00am - 3:00pm
Attendance: ALL

The day begun with a Stand-up meeting in which both sub-teams presented

1. What they have done since yesterday
2. What they plan to do today
3. What their challenges were

Stand-up meeting results

Sub-Team A: Working on the Customer Details page and search functionality, the team indicated they have been able to make head way with regards to the Search functionality. They plan to tweek it further as well as start working on the Customer details. They still had problems with the results being generated on passing values for search. The search was not working for alphanumeric inputs , only numeric.

Sub-Team B: Working on their last Episode, the front Menu structure, they indicated that was what was left to be done today.

Day's activity: Teams went back to their side-by-side programming to work on the tasks assigned them. There was occasional help provided across teams when needed.

Up until now integration had been done on the Main development machine on which Sub-Team B was working on. Their episodes were easy to integrate into the overall system. Sub-Team A had more challenges with the search functionality and we were working hard to overcome them. That proved to be a major obstacle to performing any integration with the work done by sub-team A. The Visual studio IDE with its east build and test features permitted teams to check if pages and functions were working. These took sometimes seconds to execute.

Close of Day: By close of day the search functionality being worked on by Sub-Team A was working well and they could now move on to the other episodes. The Menu Structure had been completed and would be shown to the end-user for feedback. Final Integration is scheduled for Friday -Day 3

Next Meeting: 02-Sep-2011 11:30AM



Tuesday, August 30, 2011

Iteration 1 , 2nd Increment - Day 1

Date: 30-Aug-2011
Meeting time: 11:00am - 3:00pm
Attendance: ALL

In todays meeting we begun the 2nd iteration of the 1st Delivery of Customer Management. We started the day with a brief meeting to understand the the Iteration process. According to crystal clear the Iteration Cycle involves having an iteration plan (which we did in our last meeting to identify the tasks to be done based on the feedback received from end-user), Days of work which includes various integrations and episodes.
We divided our selves into the two sub-teams on which we assigned the tasks. We scheduled to have a break after 2hrs then have a Stand-up meeting to review current status, progress and identify problems.

Stand up meeting results:

Tasks Done:

• Create site together with customer
• Prompt user to confirm creation of customer
• Sorting - customer codes and site codes

• Remove Edit /Select from Grid view
• Include Details View

Tasks Undone:


• Modify menu structure - Not yet started
• Customer Search on code and name - Problems found
• Create site for existing customer - Problems found
• Add Correspondence site among customer sites -  Not yet started


Next meeting: 31-Aug-2011 11:00am

SCREEN DRAFTS

Main Menu Screen

Create Customer Page

Add Site page

Customer details page

Search page

Tuesday, August 16, 2011

1st Iteration meeting with User

Date: Tue , 16-Aug-2011
Meeting time: 1:00 pm -2:00 pm
Venue: TG offices
Attendance: ALL

We were able to get our first working system (Walking skeleton) showing just the creation of customer and creation of customer sites

Other outputs include:
  • Refined Project Plan
  • Refined Use case models
Meeting with use yield useful feedback for system modification.  We will discuss these in our iteration plan meeting

Next meeting: Wed 17-Aug-2011 11:00 am



Wednesday, August 10, 2011

Iteration 1 , 1st Increment - Day 1

Date: Wed, 10-Aug-2011
Meeting: 11:30am - 3:30pm
Venue: Sheppard Library S223
Attendance: ALL

Agenda:

  1. First Requirements review
  2. Database design review
  3. User interface discussion and drawing on story board
  4. ASP.NET and C# discussion and demonstration
  5. Start development

Following the meeting with user yesterday we are to tackle Customer Management Increment
Mainly the Creation of Customer, Update of Customer and Creation of Site for Customer Interfaces

We looked at the database design which was already implemented by Durand from the design by Sara.

We took to the story board to manually draw and discussed what the interface should look like

Using the flat screen projector in our meeting room, we were able to demonstrate the use of the Visual
Studio IDE and the creation of ASP.NET website and pages. We all discussed as the development
progressed.

Outputs:

  • User Interface design of Customer Creation was working
  • User Interface design of Customer site creation - not working  - Reason: Must learn how to pass values from page to page 

Next Meeting: Friday 12/08/11 11:00am to get functionality working

Tasks:
Edward , Aylin, Durand : Find out more about how to pass values and get functionality working